The crew from Mortenson Construction continues to plow through the remodel at the Reardon Rectory. This week, the drywall will be installed on the fourth floor by a custom drywall company. A floor below, on the south side, the recently drywalled office space and dining room will have trim and doors installed, followed by an intense cleaning.

The kitchen is nearing completion as it is being sanded and will be ready for paint by the end of the week. On the north side of the third floor, fire protection is being added and the second floor currently has ductwork being installed.